As of October 2026, TVA has not decided how it will fix the spillway at Chatuge Dam, and no project drawdown is under way. Lake Chatuge is running on its normal seasonal schedule. TVA’s project page, last updated January 16, 2026, puts a decision in early 2027 and says construction could begin between summer 2028 and fall 2029.
This explainer sums up what TVA has published, with dates, so you can tell what may have changed since. The TVA Chatuge Dam Safety Modifications page is the place to check for anything newer. The dam is in Clay County, North Carolina, and the lake behind it reaches south into Towns County, Georgia, so owners and visitors on both shores share the same project.
Why TVA is looking at the spillway
Chatuge Dam is an earth-fill dam that TVA finished in 1942. Its spillway is a chute on the east bank that narrows into a straight concrete channel 90 feet wide and 1,356 feet long, according to the dam’s National Register nomination.
In its April 2025 notice in the Federal Register, TVA said the chute slab of that primary spillway is in poor condition and, in a rare flood, poses a dam safety risk outside TVA’s tolerances. That notice opened the environmental review that is still running.
TVA did not wait for the review to act. Beginning in December 2023, the notice says, TVA added monitoring and inspections of the spillway, repaired joints, sealed cracks in the spillway slab and walls, and supplemented the dam’s Emergency Action Plan for spillway failures.
The timeline, as TVA published it
| When | Step | Source |
|---|---|---|
| April 2025 | Notice of intent published in the Federal Register | Federal Register |
| Fall/Winter 2026 | Draft Environmental Impact Statement issued, then a 45-day public comment period | TVA |
| Late 2026 or early 2027 | Final Environmental Impact Statement | TVA |
| Early 2027 | Decision on which alternative to build | TVA |
| Summer 2028 to fall 2029 | Construction of the selected alternative could begin | TVA |
We checked TVA’s project page and the Federal Register on November 4, 2026, and no Draft EIS had been published. TVA says the public will have 45 days to comment once it is published. If you own on the lake, or simply care about it, check the project page and watch for that comment window.
The alternatives TVA is weighing
TVA has already narrowed the field. It eliminated Alternative B, which would have reconstructed the contraction joints in the concrete spillway. The project page describes the remaining action alternatives, labeled C, D and E, explains what each would build, and says how long the lake would be lowered under each:
- Alternatives D and E: drawdowns during off-season portions of up to two nonconsecutive years.
- Alternative C: drawdowns during off-season portions of up to two consecutive years.
No alternative has been selected, and TVA does not expect a decision until early 2027. Anyone who tells you the drawdown years are set is ahead of TVA.
What the 1,908-foot figure means
If TVA picks one of the action alternatives, its project page says it would reduce the water level to elevation 1,908 feet, about 10 feet below the current winter level. Drawdowns would be planned for off-season months, late summer to early spring.
For scale, TVA’s normal guide curve for Chatuge bottoms out at 1,915 feet in mid-February and peaks at 1,926 feet around Memorial Day, per the Federal Register notice. The flood guide runs from 1,918 feet in winter to 1,926 feet in summer. That puts 1,908 feet roughly 7 to 10 feet below normal winter levels and about 18 feet below the summer target. Those gaps are our arithmetic from TVA’s figures, not a TVA forecast.
The part owners ask about most is the refill. TVA says the return to summer water levels after a drawdown would rely on rainfall, and that levels cannot be guaranteed.
TVA says refilling to summer levels after a drawdown depends on rainfall and cannot be guaranteed. (TVA, checked Oct 31, 2026)
One note on older coverage. TVA’s spring 2025 notice described longer drawdowns. TVA has since revised its plans, and its January 2026 project page describes off-season drawdowns only. For durations, rely on the project page rather than the 2025 notice or news stories based on it.
What it means right now
For visitors
As of October 2026, the project does not change a trip. There is no project drawdown, and TVA’s timeline puts the construction start between summer 2028 and fall 2029. The lake follows its usual pattern: in a year with normal rainfall, TVA says the level varies about 10 feet from summer to winter for flood storage. TVA posts observed levels through the day and predicted levels at least once a day by 1 p.m. Eastern on its Chatuge lake-level page. Our lake levels guide explains the yearly curve.
Lake level
1,915–1,926 ft
TVA’s guide curve runs from about 1,915 ft in mid-February up to 1,926 ft around Memorial Day, a swing of roughly 10 feet. Federal Register (TVA, 2025) Today’s reading is posted on TVA’s Chatuge lake-levels page.
For owners and buyers
- Know how much water your dock has at normal winter levels, then picture it 7 to 10 feet lower. That is the gap between today’s winter levels and the 1,908 feet TVA described.
- Any work on a dock or the shoreline needs a TVA Section 26a permit first, even minor changes. Our 26a dock permit guide covers fees, timing and the 60-day rule for new owners.
- If you are buying, read the TVA project page before you close and note the date you read it. The rest of the buyer homework is on our Lake Chatuge homes page.
- Watch for the Draft EIS comment period. It is the formal chance to tell TVA how a drawdown would affect you.
Boaters: a low winter lake, and any future drawdown, changes which launches work. Our Lake Chatuge boat ramps guide lists every public ramp an agency publishes on both shores, with low-water notes. We re-checked the Federal Register on October 28, 2026: TVA’s April 21, 2025 notice of intent is still the latest Chatuge Dam filing, so no Draft EIS had been published as of that date. We re-checked TVA’s project page on October 31, 2026: it still carries the January 16, 2026 update and now gives the construction window as summer 2028 to fall 2029.
Where to follow it
TVA’s project page is the primary source, and every date on this page comes from it or from the 2025 Federal Register notice. We will update this explainer as TVA publishes new steps. For the dam’s own story, from its 1941 start to its 2017 listing on the National Register of Historic Places, see our Lake Chatuge history page. The crest of the dam is a public walking trail, and our dam walk guide explains where it runs.
Questions about the Chatuge Dam safety project
Is TVA draining Lake Chatuge?
As of October 2026, no. TVA has not selected an alternative for the spillway project, and no project drawdown is under way. TVA says construction of a selected alternative could begin between summer 2028 and fall 2029.
Source: TVA, checked Oct 17, 2026
How low would Lake Chatuge go during the spillway project?
If TVA chooses one of the action alternatives, its project page says the lake would be lowered to elevation 1,908 feet, about 10 feet below the current winter level, during off-season months from late summer to early spring.
Source: TVA, checked Oct 17, 2026
Would the lake refill after a drawdown?
TVA says the return to summer water levels after a drawdown would rely on rainfall, and that levels cannot be guaranteed.
Source: TVA, checked Oct 17, 2026
When will TVA decide on the Chatuge Dam spillway fix?
TVA's timeline, updated January 16, 2026, lists a Draft EIS for fall or winter 2026, a Final EIS for late 2026 or early 2027 and a decision in early 2027, with construction beginning between summer 2028 and fall 2029.
Source: TVA, checked Oct 17, 2026